Goals and critical path

Sources & anchors

  • Stack component: Orchestration
  • Canonical artifact: [example: TBD] — goal-arash-20260507-221912-674817 anonymized
  • Workshop session: Day-3 PM closing
  • Outline: _outline.md §B

Frame

Goal definition, milestones, critical-path computation, weekly focus().

The planning gap the goal engine fills

The previous chapter introduced four orchestration components: registry, captures, queue, goals. The first three are event-driven — they react to whatever the researcher and the agent do. The fourth is control-driven — it shapes what should be done next, given deadlines and dependencies.

Research has no shortage of events. The shortage is a way to answer three questions on Monday morning:

  1. What matters right now?
  2. What should I do next?
  3. What is drifting or blocked?

Tasks alone do not answer these. A flat list of fifteen pending tasks across six projects has no priority signal beyond what each task note declared at creation time, no awareness of which deadlines have moved closer since, and no model of which work blocks which other work. The goal layer adds the missing structure.

Goal notes

A goal is a markdown note in docs/log/goal/ with frontmatter that declares its planning identity:

---
id: agentic-workshop-2026-09
title: "Deliver agentic-research workshop (4-day department course, Sept 2026)"
status: active
priority: 1
target_date: "2026-09-30"
progress: null
projects: [projio]
tags: [workshop, handbook, teaching]
---

## Objective
Deliver a 4-day practical workshop on the agentic research workflow…

## Milestones
1. Workspace provisioned — `teaching/agentic-workshop/` exists,
   registered in the orchestration registry, Quarto project
   scaffolded. (Target: 2026-05)
2. Announcement finalized & sent. (Target: 2026-06)
3. Syllabus drafted. (Target: 2026-07)
4. Day 1–3 materials drafted. (Target: 2026-08)
5. Dry run with 1 volunteer. (Target: mid 2026-09)
6. Workshop delivered (days 1–4). (Target: late 2026-09)
7. Post-mortem captured. (Target: early 2026-10)

The id is stable — once tasks reference a goal by id they must not be silently renamed. Goal status follows a strict lifecycle: active → paused | done | dropped. Priority is a manual ranking band from 1 (critical) to 3 (nice-to-have). target_date is optional but unlocks the urgency component of the agenda score; progress is an optional 0–100 estimate that drives goal pressure.

The body sections are conventional but matter for the engine. The Milestones list is the goal's decomposition into checkpoints. The Cross-references section is where related ideas, prior task notes, and dependent goals get cited. Both feed the critical-path view.

Tasks gain four optional fields when a goal layer is in use:

Field Type Default Purpose
priority int 2 1–3 manual ranking, same scale as goals
due ISO date "" Task-level deadline
goal string "" The goal id this task contributes to
blocked bool false Whether the task is externally blocked
blocked_by string "" Free-text explanation (only when blocked: true)

These are additive. A task without goal: ... is unassigned and shows up in the agenda's unassigned tasks bucket. The agenda treats this bucket as a low-priority backlog — visible, but not part of the critical path.

The agenda

agenda() (MCP) and worklog agenda (CLI) compute the prioritized view that the planning loop consumes:

{
  "generated": "2026-05-11T10:00:00+02:00",
  "goals": [
    {
      "id": "agentic-workshop-2026-09",
      "title": "Deliver agentic-research workshop…",
      "priority": 1,
      "target_date": "2026-09-30",
      "days_remaining": 142,
      "progress": 40,
      "pressure": 0.42,
      "projects": ["projio"],
      "tasks": [
        { "title": "Draft handbook chapter 80-orchestration",
          "status": "pending", "priority": 2, "due": "",
          "project": "projio", "blocked": false, "score": 4.42,
          "path": "docs/log/task/..." }
      ]
    }
  ],
  "unassigned_tasks": [ /* pending tasks with no goal link */ ],
  "drift": [
    { "project": "cogpy", "days_silent": 4,
      "goals": ["agentic-workshop-2026-09"],
      "message": "cogpy: 4d silence, linked to workshop goal" }
  ],
  "next_action": {
    "title": "Draft handbook chapter 80-orchestration",
    "project": "projio",
    "goal": "agentic-workshop-2026-09",
    "reason": "P1 goal | goal pressure 0.42 | pending"
  }
}

The four fields encode the planning loop:

  • goals — active goals, each annotated with pressure (how hard the goal is pushing on attention now), days_remaining, and the list of tasks attached to that goal.
  • unassigned_tasks — pending and active tasks with no goal link; the backlog.
  • drift — projects with no recent commits, captures, or queue activity but with active goals attached. The orchestration layer flags these so they don't quietly stall.
  • next_action — the single highest-ranked task, with the reason it ranks first.

Ranking: bands first, scores second

The agenda ranks tasks in two stages.

Stage 1 — priority bands. Tasks are grouped by their effective priority, which is min(task.priority, goal.priority) when a goal exists. A priority-2 task under a priority-1 goal gets promoted to band 1. A task in band 1 always ranks above every task in band 2, regardless of any computed score. Manual priority dominates.

Stage 2 — score within band. Inside each band, tasks sort by a score combining three signals:

Signal What it captures
goal_pressure (100 − progress) / max(days_remaining, 1), capped at 10. Higher when the goal is behind and the deadline is near. 0 when no goal or no deadline.
due_urgency Overdue → 10; due today → 7; due in N days → 7 / N; no due date → 0.
status_boost +1 if the task is already in progress (status: active), 0 otherwise.

The result is a number — useful for ordering, not for treating as a measure of importance. Bands carry the importance; scores break ties within a band.

Critical path

The critical_path field on each goal is the ordered list of pending tasks whose dependencies block the goal's earliest milestone. The orchestration layer computes it by walking task depends_on declarations and milestone references in the goal body. Where a task declares no dependencies, it joins the critical path by recency on the goal's last open milestone.

The critical path is a suggestion, not an authoritative scheduler. The researcher reviews it, accepts or adjusts the order, and dispatches the next step. The system never decides what to run unprompted.

Weekly focus()

focus() is the planning surface that turns the agenda into a weekly contract. It selects a small set of goals (or accepts an explicit list) and pins them as this week's focus. The CLI:

worklog focus                          # show this week's focus
worklog focus -g workshop,handbook     # pin two goals
worklog focus --clear                  # reset

The pinned focus is consumed by every other tool in the orchestration layer:

  • agenda() highlights tasks under focused goals.
  • Dispatch tools default to focused goals when no project is given explicitly.
  • The drift detector raises warnings sooner for projects attached to the focused set.

The contract pattern is soft: focus does not prevent unrelated work, it just changes what the planning surface foregrounds. The researcher promises themselves they will spend most of the week on the focused goals; the system makes that promise easier to keep.

Capacity

capacity() complements focus(). It records the researcher's declared availability in plain text:

54% session 2h25m | 69% weekly resets Wed 5PM

The orchestration layer reads this when ranking tasks: a long-running dispatch (opus, multi-file) is deprioritized when session capacity is near the cap; short tasks (haiku, single-file) are preferred. The mechanism is intentionally soft — capacity is a hint, not a hard schedule.

The canonical example

The first end-to-end goal exercised in this repository is the workshop goal cited at the top of this chapter. Its file (an anonymized form of docs/log/goal/goal-arash-20260507-221912-674817.md) contains:

  • Stable id (agentic-workshop-2026-09) referenced by every handbook drafting task.
  • A target date (2026-09-30) and milestones expressed as a numbered list with their own sub-deadlines.
  • A projects: list ([projio], since the workshop materials live in this repo) — though the work it enables touches several others.
  • An Objective paragraph explaining what "done" looks like and a Why this goal matters section that names the constraints (the LSM Future Skills slot fixes the date; competing work on TAC
  • manuscript writing constrains the path).
  • A Cross-references pointer to the originating idea note, so someone reading the goal cold can recover the design context.

That goal directly produced the task notes used to draft this chapter and its siblings, and produced this very page as a result. The captures → tasks → goals → result loop is the artifact this chapter is teaching.

Honest gap: goal coverage is shallow

At the time of the cohort survey, exactly one goal note exists in the cohort (the workshop goal above). The goal engine is implemented and exercised; the practice of authoring goal notes is not yet a baseline discipline. The handbook treats the goal layer as a graduated practice: install the surface, but expect a project to accumulate its first goal only when it has multiple concurrent deadlines worth coordinating. See 99-honest-gaps.md for the broader cross-cutting context.

The final chapter closes the loop: how the orchestration layer turns a captured observation, ranked against a goal, into a queued dispatch that returns a result note.